当前位置: 首页 精选范文 通信工程的定义

通信工程的定义范文

发布时间:2023-10-11 15:55:06

导语:想要提升您的写作水平,创作出令人难忘的文章?我们精心为您整理的5篇通信工程的定义范例,将为您的写作提供有力的支持和灵感!

通信工程的定义

篇1

Abstract: at present, flourished and burgeoning urban construction, in the development of urban traffic construction and saving land resources there is always opposition and unity. Social development process is also constantly and progress to the end of the process, for increasingly scarce land resources at present, under the underground interchange Settings for its advantage on saving and environmental protection chosen by people gradually. Under the underground interchange often takes the form of Ming WaFa pouring reinforced concrete underground passage, the author through the construction practice, segmentation and flow in to such construction structure, the construction of the core link - the top mold racks of turnover has made some research on the system, in the save construction time limit for a project, to ensure construction safety, reduce the human resources investment, saving construction cost, etc are summarized.

Key words: underground interchange; Top mold racks; The whole time.

中图分类号:U445.4文献标识码:A文章编号:2095-2104(2013)

0. 前言

项目简介:富阳东大道项目市政基础设施地下道路工程属于明挖型现浇钢筋混凝土地下通道,断面结构为单层单箱双室形式,南北双线双向四车道,工程施工主要以钢筋混凝土作业为主,地下通道路线全长1.77公里,单幅净宽8.8米,净高5.4米,全线共设置68道横向变形通缝,将结构分割成69段长度基本均等的结构段,全线横断面形式相对单一,整个结构施工作业属于线条型循环流水作业。针对工程特点,经过反复的计算和邀请专家进行论证,最终确定使用HR系列可调门式满堂支架作为主体结构顶模的承重支撑架。

需要解决的困难:根据富阳市政府的要求,用于主体结构施工的时间只有14个月,在有限的时间内需要完成1.77km共计69段结构,工期非常紧张。鉴于工期紧张的情况,项目部提出了在保证质量和安全的前提下,必须解决工期紧张的问题,按时完工。项目团队在经过充分调查和分析传统的施工工艺前提下,将解决困难的途径放在如何节省通道单段施工时间上。

1.传统施工工艺的现况调查

解决困难的方向确定后,在工程施工现场,笔者选择了现场某一施工段进行了调查。调查内容为采用常规施工方法对通道顶板施工时,各施工环节的时间分配。在调查过程中,现场投入的支撑架施工班组人、机、料等按照标准配置,通过对整个施工流程进行了工艺耗时方面的统计,统计情况如下图。

经过对现况的调查,笔者对循环作业各个环节所消耗的时间进行分析。笔者认为在施工班组人、机、料等按照标准配置的情况下,钢筋安装、混凝土浇筑和养护时间基本属于不变时间。但在循环作业中,内模板的拆除和安装,支架的拆除和再搭设等支撑架转移的环节共计15天,这些环节能通过减少拆除和搭设时间来节省循环时间。

2.具体措施

2.1 提出减少支架搭拆循环工艺耗时的方案

笔者通过对现场施工一线的询问和调查,困扰工人施工速度的最大的阻碍,是在有限的空间里对大量的门架、杆件进行重复拆装作业上的时间耗费,普遍一个想法是要是能让整套模架动起来就方便了。笔者给予上述想法,构思了一个全新的方案:模架达到拆除要求后,将侧模板拆除就近挂靠于支架上,然后给支架底安装一定数量的滑轮,人工撬动为主,借用转扬机动力的辅助,使支撑架整体向前推移,来缩短支架周转的时间。材料选择与检验

2.2 制订了具体施工工艺流程图

2.3 实施过程中出现的问题

笔者按照设想的流程,通过对现场实验,在实施过程中发现有如下几方面的问题出现,并需要解决:

1)、滑轮安装的数量多少;

2)、滑轮与支架结合点的最佳位置;

3)、行进间如何对支撑架进行导向;

4)、推移动力的选择与组合并使其达到最佳;

5)、混凝土面产生的阻力过大,任何解决推移困难的问题。

2.4 提出问题解决的对策并付诸实践

笔者通过反复分析和总结,提出了针对问题的对策,并在现场对对策付诸了实践,从如下几个方面实践:

1)、滑轮安装的数量多少——通过计算支撑架的总重来确定滑数量和滑轮距离

按照支架设计方案,取长度为15米支撑架进行自重计算,计算出支撑架总重25吨。按照厂家提供的滑轮承重荷载能力为1.25吨,25/1.25=20个,按照24个布置,横向4个,纵向6个,可以得出每只滑轮实际承重为25/24=1.04吨

2)、滑轮与支架结合点的最佳位置——找将滑轮安装于横向扫地杆、门架立杆和门架大横杆三点交结处

根据分析,每一个滑轮需要承受1.04吨的重量,每一个单根杆件和扣件都不能承受这个重量。根据支架的搭设特点,笔者最终将滑轮安装于横向扫地杆、门架立杆和门架大横杆三点交结处。安装如图示。

3)、行进间如何对支撑架进行导向——放样划线后,过程及时进行方向纠偏

对结构底板表面进行清理后,测量人员对支撑架的位置进行放样,在结构底板表面画好滑轮的正确行进线路。在推移过程中技术人员全程进行观察,当发现方向偏移时,利用滑轮为万向轮的特点,用撬棍及时调整方向,再次滑移过程中进行纠偏,达到定位的目的。

4)、推移动力的选择与组合并使其达到最佳——以人工集中撬动为主,转扬机辅助

支撑架属于杆件组合支架,整体移动时容易晃动,加之底板表面较粗糙,在移动过程中摩擦阻力和晃动的惯性都不停的变化。转扬机作为动力牵引时,牵引力总是处于均匀不间断受状态下。笔者分析如果单纯采用转扬机进行牵引,不适合支架的整体移动,因此笔者决定在架体外设置一个转扬机的同时,采用8—10人均有分布支撑架内,同时集中撬动,使支架有频率的在瞬间同时受力,达到推动之间的目的。

5)、混凝土面产生的阻力过大,如何解决推移困难的问题——根据每模支撑架的长度,将移动单元分成10—15米不等的长度进行推移

有些结构段底板表面过于粗糙,或者处于上坡段,或者处于加款段,或者加长段等。针对每一段结构都有一些特殊的情况,笔者对不同支架根据每模支撑架的实际情况,将移动单元分成10—15米不等的长度进行推移,现场灵活机动的处理,达到快速便捷移动的目的。

4.结论

笔者通过对上述过程的总结,得出了如下结论:

1、 针对问题的出现,通过创新来解决问题,在实践过程中需要大力发扬和提倡;

2、通过实践统计,发现支架周转的时间从原来的15天控制到7天以内,节省了大量的时间;

3、此法不但达到了节省工期的目的,更加明显的是节省了施工成本。单从人工方面计算,按照市场工人平均90元/工,可以计算出每段人工费用节省6480元,东大道项目共计施工段69段,共计可节省人工费用44.7万元。

4、在节省人力资源的同时,还节省了门架、钢管等材料的租赁费,节省了模板上下搬运的损伤损耗费,节省抢进度带来了管理费等等方面。

5、通过这次创新活动,在针对大型地下通道顶模支撑架整体推移施工工艺上总结了施工经验,对今后同类工程施工有指导作用。

参考文献

1、《建筑施工模板安全技术规范》JGJ162-2008

2、《建筑施工门式钢管脚手架安全技术规范》(JGJ128-2000)

篇2

[中图分类号] R541.4 [文献标识码] A [文章编号] 1673-7210(2017)01(c)-0160-04

[Abstract] Objective To investigate the effect of Ivabradine on stable angina pectoris and its influence on vascular endothelial function and atherosclerosis. Methods One hundred and seventy patients with stable angina pectoris admitted to Department of Cardiology, General Hospital of Benxi Iron and Steel Co.,Ltd. from January 2012 to January 2015 were selected and randomly divided into two groups by random number table. 85 cases of control group were treated with Atenolol, 85 cases of observation group were treated with Ivabradine. The clinical curative effect and the changes of vascular endothelial function and arteriosclerosis status before treatment and after treatment for 4 weeks were compared. Results The difference of the clinical curative effect between the two groups was statistically significant (u = 2.814, P < 0.05). After treatment, the resting heart rate (RHR), exercise heart rate (EHR), angina attacks times and duration of the observation group were much lower or shorter than those of control group (P < 0.05). After treatment, the levels of nitric oxide (NO) and superoxide dismutase (SOD) in the observation group were much higher than those in control group, the levels of endothelin-I (ET-1), malondialdehyde (MDA) and the value of brachial-ankle pulse wave velocity (baPWV) in the observation group were much lower than those in control group (P < 0.05). Conclusion Ivabradine in the treatment of stable angina pectoris can decrease the RHR and EHR effectively, and also can improve the vascular endothelial function and arteriosclerosis status, which has definite therapeutic effect.

[Key words] Stable angina pectoris; Ivabradine; Vascular endothelial function; Arteriosclerosis

定型心绞痛(stable angina pectoris,SAP)是一种病理基础简单的冠状动脉疾病,临床表现为下颌、上臂、胸或肩背憋闷疼痛[1-2]。不少研究显示[3-4],血管内皮功能的损伤、冠状动脉的狭窄及硬化易诱发冠脉不良事件的发生。故临床治疗中,缓解SAP临床症状的同时,更应关注患者血管内皮功能及动脉硬化程度。伊伐布雷定[5-6]是一种特异性、选择性If电流抑制剂,通过减慢患者心率,降低心肌耗氧量,有效缓解心绞痛。目前,有关伊伐布雷定对患者血管内皮功能及动脉硬化情况的影响鲜有报道。本文旨在研究该药对SAP患者血管内皮功能及动脉硬化情况的影响,以期探讨其临床疗效及预后效果。

1 资料与方法

1.1 一般资料

本研究对象为辽宁省本溪市本钢总医院心内科2012年1月~2015年1月收治的170例SAP患者,其中,男65例,女105例,年龄40~67岁,平均(50.1±4.5)岁。纳入标准:①符合《慢性稳定型心绞痛诊断与治疗指南》[7]的诊断标准,且心绞痛CCS分级Ⅰ~Ⅲ级。②具有心绞痛症状,且符合下列条件之一或多项:冠脉介入或冠脉搭桥术超过6个月;心肌梗死超过3个月;缺血型心电图改变;冠脉造影显示一条或多条冠状动脉口径狭窄超过50%;心绞痛发作时,心电图结果出现ST段抬高超过1.0 mm或P-R段相比旱统过1.0 mm。③运动平板试验结果阳性。④左心室射血分数超过50%。⑤病史超过3个月。⑥对本研究知情,且自愿签署知情同意书。排除标准:①急性心力衰竭或急性冠脉综合征者。②先天性心脏疾病或心脏瓣膜疾病者。③慢性肺部疾病或脊柱畸形者。④合并内分泌疾病者。⑤神经肌肉疾病者。⑥3个月内服过胺碘酮或7 d内服过非二氢吡啶类、β受体阻断剂等抗心律失常药者。⑦长期酗酒者。⑧合并心律失常或静息状态下心率低于60次/min者。

按照随机数字法将入选者分为两组。对照组85例,其中男30例,女55例;平均年龄(49.8±5.1)岁;平均病程(5.1±0.4)个月;心绞痛CCS分级Ⅰ级32例,Ⅱ级38例,Ⅲ级15例。观察组85例,其中男35例,女50例;平均年龄(51.0±4.7)岁;平均病程(5.8±0.7)个月;心绞痛CCS分级Ⅰ级30例,Ⅱ级41例,Ⅲ级14例。两组患者性别、年龄、病程、心绞痛CCS分级方面差异无统计学意义(P > 0.05),具有可比性。此外,本研究获得医院伦理委员会批准。

1.2 方法

所有患者均给予基础药物治疗,主要包括他汀类降脂药、血管紧张素Ⅱ受体拮抗剂、血管紧张素转换酶抑制剂、阿司匹林等药物治疗,剂量按说明书服用。观察组给予伊伐布雷定(辰新药业股份有限公司,批号:201325),5.0 mg/次,每天2次。对照组给予阿替洛尔(辰新药业股份有限公司,批号:201134),15.5 mg/次,每天2次。持续治疗4周。

1.3 观察指标

所有患者于治疗前和治疗4周后进行检查。①疗效评价[8]:症状显著减轻,且同程度运动量患者心绞痛发作频率减少≥80%,或未出现过心绞痛视为显效;症状相对减轻,同程度运动量患者心绞痛发作频率减少50%~

1.4 统计学方法

采用SPSS 19.0软件包进行统计学分析,计量资料以均数±标准差(x±s)表示,采用t检验;计数资料以例数或百分比表示,采用χ2检验;等级资料比较采用秩和检验。以P < 0.05为差异有统计学意义。

2 结果

2.1 两组临床疗效比较

秩和检验分析发现,两组临床疗效比较,差异有统计学意义(u = 2.814,P = 0.005)。见表1。

2.2 两组治疗前后心率变化情况比较

治疗前,两组患者RHR及EHR比较,差异无统计学意义(P > 0.05)。经不同方法治疗后,观察组RHR及EHR较治疗前显著降低,且均明显低于对照组,差异有统计学意义(P < 0.05)。见表2。

2.3 两组治疗前后心绞痛发作频率、持续时间比较

治疗前,两组患者心绞痛发作频率、持续时间比较,差异无统计学意义(P > 0.05)。经不同方法治疗后,观察组心绞痛发作频率较治疗前显著减少,心绞痛发作持续时间较治疗前显著缩短,且均明显低于对照组,差异有统计学意义(P < 0.05)。见表3。

2.4 两组血管内皮功能标志物水平变化比较

治疗前,两组患者血清中NO、ET-1、SOD和MDA水平比较,差异无统计学意义(P > 0.05)。经不同方法治疗后,观察组NO和SOD水平较治疗前显著升高,且明显高于对照组,差异有统计学意义(P < 0.05),ET-1和MDA水平较治疗前显著下降,且明显低于对照组,差异有统计学意义(P < 0.05)。见表4。

2.5 两组治疗前后肱-踝脉搏波传导速度变化比较

治疗后,两组患者baPWV均显著低于治疗前(P < 0.05),且观察组治疗后baPWV明显低于对照组,差异有统计学意义(P < 0.05)。见表5。

3 讨论

研究发现[9],心绞痛发病多因心肌供需氧不平衡所致,故临床上常用减少心肌耗氧或增加冠脉流量的方法缓解心绞痛症状。扩血管药物在增加冠脉流量方面虽效果明显,但当患者冠脉钙化时,扩管效果则较难实现[10]。减慢心率、降低心肌耗氧量的抗心绞痛药物逐渐成为治疗心绞痛重要的途径[11-13]。伊伐布雷定通过抑制心脏窦房结内If电流,延长心脏动作电位时间间隔,降低窦房结节律,降低患者心率,降低心肌耗氧量,达到控制心绞痛的效果[14-17]。本研究结果也发现,观察组治疗后RHR及EHR明显降低,心绞痛发作频率及持续时间也明显低于或短于对照组,说明伊伐布雷定对SAP的治疗效果明确。

据报道,NO、ET-1、SOD和MDA水平与血管内皮功能损伤具有密切关联[18]。其中NO是一种重要的舒血管物质,它与ET-1相互保持平衡,维持血管正常收缩及舒张特性;ET-1具有强烈的缩血管功能,参与缺血性脑血管疾病的病理过程,且该指标的升高与梗死面积大小相关[19-20];SOD能对抗氧自由基对细胞的损害,同时修复受损细胞[17]。MDA则在血管内皮细胞受损时会明显升高,反映血管内皮特性[21]。研究发现,两组患者血浆中ET-1和MDA水平在治疗后均明显下降,与治疗前相比差异有统计学意义(P < 0.05),但观察组治疗后ET-1和MDA水平^对照组明显偏低;两组患者血浆中NO和SOD水平在治疗后均明显升高,与治疗前相比差异有统计学意义(P < 0.05),但观察组治疗后NO和SOD水平较对照组明显偏高;说明两种治疗方法对患者内皮均具有保护作用,其中伊伐布雷定对患者内皮的保护作用更为显著。这可能与以下几点内皮保护机制有关:①下调血清中低氧诱导因子-1α表达,拮抗内皮细胞凋亡[22];②降低血清中血管内皮生长因子浓度,修复受损内皮细胞[23-24];③平衡体内NO与ET-1水平,维持血管正常收缩及舒张特性,减少梗死面积[25];④平衡体内SOD与MDA水平,修复受损细胞。

baPWV主要反映动脉搏动由近心端向远心端的传导速度,是反映动脉硬化程度的黄金指标。研究表明,当baPWV值增加时,患者的冠心病进展程度会随之加快,且相关不良危险因素会随之产生[26]。本研究发现伊伐布雷定能有效减低baPWV值,这可能由于其能够增加血浆中去甲肾上腺素浓度,改善冠脉血流。

总之,伊伐布雷定治疗SAP患者,能够有效降低患者静息状态及运动量心率,减少心绞痛发病次数及病发持续时间,能够有效改善患者血管内皮功能和动脉硬化情况,疗效确切。

[参考文献]

[1] Füeβl HS. Stable angina pectoris:assessment [J]. MMW Fortschr Med,2016,158(10):10-14.

[2] Valgimigli M,Biscaglia S. Stable angina pectoris [J]. Curr Atheroscler Rep,2014,16(7):422-423.

[3] Fishbein MC,Fishbein GA. Arteriosclerosis:facts and fancy [J]. Cardiovasc Pathol,2015,24(6):335-342.

[4] T?ille M,Reshetnik A,Schuchardt M,et al. Arteriosclerosis and vascular calcification:causes,clinical assessment and therapy [J]. Eur J Clin Invest,2015,45(9):976-985.

[5] Ye L,Ke D,Chen Q,et al. Effectiveness of ivabradine in treating stable angina pectoris [J]. Medicine(Baltimore),2016,95(14):e3245-3247.

[6] Tendera M,Borer JS,Tardif JC. Efficacy of I(f)inhibition with ivabradine in different subpopulations with stable angina pectoris [J]. Cardiology,2009,114(2):116-125.

[7] 中华医学会心血管病学分会.中华心血管病杂志编辑委员会.慢性稳定型心绞痛诊断与治疗指南[J].中华心血管病杂志,2007,35(3):195-206.

[8] 中华人民共和国卫生部医政司.中国常见心脑血管疾病诊治指南[M].北京:科学出版社,2000:59-60.

[9] Parker JD,Parker JO. Stable angina pectoris:the medical management of symptomatic myocardial ischemia [J]. Can J Cardiol,2012,28(2 Suppl):S70-S80.

[10] Wang FF,Han JL,He R,et al. Prognostic value of coronary artery calcium score in patients with stable angina pectoris after percutaneous coronary intervention [J]. J Geriatr Cardiol,2014,11(2):113-119.

[11] Feng J,Wang A,Gao C,et al. Altered heart rate variability depend on the characteristics of coronary lesions in stable angina pectoris [J]. Anatol J Cardiol,2015,15(6):496-501.

[12] Zagidullin N,Scherbakova E,Safina Y,et al. The impact of remote ischemic preconditioning on arterial stiffness and heart rate variability in patients with angina pectoris [J]. J Clin Med,2016,5(7):E60-E63.

[13] Tendera M,Fox K,Ferrari R,et al. Inadequate heart rate control despite widespread use of beta-blockers in outpatients with stable CAD:findings from the international prospective CLARIFY registry [J]. Int J Cardiol,2014, 176(1):119-124.

[14] Giavarini A,de Silva R. The role of ivabradine in the management of angina pectoris [J]. Cardiovasc Drugs Ther,2016,30(4):407-417.

[15] ,钟伟州.盐酸曲美他嗪治疗冠心病稳定型心绞痛的效果观察[J].中国医学创新,2015,12(14):52-54.

[16] 尚士国,郭琴.冠心病与血清同型半胱氨酸相关性的临床研究[J].中国现代医生,2015,53(17):20-21,24.

[17] 何卫斌,杨桂.冠心病患者血浆同型半胱氨酸、白细胞介素-6、B型利钠肽的表达及临床意义[J].中国医药导报,2015,12(14):50-52,70.

[18] 张腾,李岳春,革丽莎,等.伊伐布雷定对病毒性心肌炎小鼠的心功能和儿茶酚胺作用[J].中国临床药理学与治疗学,2015,20(8):859-864.

[19] 李建兰.老年冠心病患者超敏C反应蛋白、D-二聚体的相关性研究[J].中国现代医生,2015,53(13):114-117.

[20] Lee JY,Ryu S,Lee SH,et al. Association between brachial-ankle pulse wave velocity and progression of coronary artery calcium:a prospective cohort study [J]. Cardiovasc Diabetol,2015,4(14):147-149.

[21] Zhang F,Wu SZ,Zhang L,et al. Effects of simvastatin on plasma SOD,MDA and 8-iso-PGF2α in patients with stable angina [J]. Nan Fang Yi Ke Da Xue Xue Bao,2010, 30(12):2646-2648.

[22] Ates O,Azizi S,Alp HH,et al. Decreased serum paraoxonase 1 activity and increased serum homocysteine and malondialdehyde levels in age-related macular degeneration [J]. Tohoku J Exp Med,2009,217(1):17-22.

[23] S通,骆众星,周华,等.N末端脑钠素原水平与冠心病患者 危险分层及全球急性冠状动脉事件注册评分的相关性[J].中国医药导报,2015,12(17):68-71.

[24] 王宝魁,刘松,徐少杰,等.伊伐布雷定对急性心肌梗死兔血清中HIF-1α和VEGF表达影响[J].青岛大学医学院学报,2013,49(1):56-58.

篇3

信息技术的快速发展,通信运营商之间的竞争越来越激烈。一些开放化的、标准化的网络协议被普遍支持,出现了面向服务架构的通信工程信息管理系统。许多通讯工程企业为了在市场迅速多得一席之地,大量高精尖的通信技术不断的被开发,这也使得通信工程更加深入化、复杂化。在这种剧烈的竞争背景下,信息系统即无法满足消费者的综合需求也无法达到企业间的商务协同自动化和智能化的需求。而新兴的面向服务的架构理论则可以面对这些问题提出有效的解决方案。

1面向服务架构的概述

在通信工程信息管理系统中,如何让其面向服务构架是现阶段主要研究的内容,而对面向服务构架而言,多数人不清楚其实际的含义,为此下文对其节本概念进行分析。

1.1面向服务架构的基本概念

面向服务架构英文简称SOA(Service-OrientedArchitecture)。SOA是一个组件模型,它的重点在于“服务”的概念,它将应用程序的不同功能单元(称为服务),通过功能单元之间定义良好的接口和契约联系起来。接口是采用中立的方式进行定义的,它应该独立于实现服务的硬件平台、操作系统和编程语言。这使得构建在各种这样的系统中的服务可以以一种统一和通用的方式进行交互。

1.2面向服务架构的基本特征

第一,从技术层面而言,SOA具有业务驱动的特点,业务需求和提供服务是双向互动关系。第二,服务请求者到服务提供者的绑定与服务之间是松合的。这就表明,服务请求者不会了解提供者实现的技术细节,即可以在不影响服务使用者的情况下调整修改服务。第三,具有可重用的服务特点。这样的设计特点很大程度上价低了成本。由于可重用服务是采用通用的格式提供重要的业务功能,这也为相关工作人员节约了时间。第四,具有明确定义的接口,SOA中的服务的交互接口必须是被明确定义和描述的。服务提供者应该使用标准的服务描述语言来定义接口,用于描述服务请求者要求绑定到服务所需要的细节。第五,SOA具有数据量低频率访问的特点。对于传统的分布式计算模型而言,他们的服务提供都是通过函数调用的方式进行的,而SOA系统则是采用自身拥有的大数据量方式一次性进行信息交换。

2通信工程信息管理系统的分析、功能设计

通信工程在实际的应用中比较广泛,其信息系统能够为企业、建筑施工方等提供较多的便利,下面我们对通信工程信息管理系统进行分析,将其功能在实际的应用加以阐述,具体内容如下:

2.1信息管理系统分析

根据上述分析,我们清楚地了解SOA这一项具体技术的应用,通过与SOA这项技术的结合,我们详细地阐述系统的各主要功能的设计与实现方法。首先,的搭建通信工程信息管理系统,将SOA做为统一的信息基础架构。其次从最初规划设计、建造实施到竣工验收,对于整个项目的不同阶段共设计了企业信息门户、协同办公管理、工程管理、物资管理、财务管理、手机智能终端六大子系统。最后各个子系统之间进行紧密无缝的连接,各系统协同工作并分工明细、权责明确。这样不仅有效简化工作流程,使得系统内部信息间的可以进行自动推送,跨部门多岗位合作,还提高通讯工程的整体工作效率,很大程度上降低信息运营成本,实现企业办公自动化,管理秩序化,决策信息化的目的。

2.2通信工程信息管理系统的特点

在现代的通信工程中,最为显著的特点为具备先进的企业信息化平台设计理念。主要是通过采用SOA架构体系,搭建通信工程信息管理系统,以工程项目管理为主要任务,并且借助每一业务与模块间的无缝连接,进而使管理工作更加的科学合理,并且对以往的管理流程进行优化。

2.3通信工程信息管理系统功能设计分析

第一,企业信息门户应用到企业内部。在企业内部能够主要实现信息管理工作,将公告通知、待办日程以及日程安排等信息资源加以整合,不同的用户可以在不同时段、不同点都能够浏览到其所需要的内容,为大家节省了许多的时间。第二,对于建设单位而言,应用通信工程信息管理系统可以借助施工任务书的形式下达施工任务,同时项目经理在接收任务之后,需要以工程的实际进度要求为依据,安排相应的工程计划实行具体内容。借助信息门户,相关的建设单位便能够及时、有效的掌握工程的实际施工进度,工程决算以及质量工艺等内容,大大的提高了建设单位的监管力度,实现了工程项目的可控性。

3结语

综上所述,通信工程信息管理系统具有先进性,综合性以及灵活可扩展性这系列优点,又能够在一定程度上便利了相关企业的实际工作,提高工作效率,因此其在国内的工程管理软件中的地位比较领先。为了更好的发展通信工程,需要我们做好相应的管理工作,并且通过引入高端人才以及先进的技术来不断创新此信息管理系统,进一步推动通信工程信息管理系统的发展。

参考文献:

[1]栾咏红,吴俊.面向服务架构的设计信息管理平台研究[J].计算机与现代化,2012(12):157~160.

[2]陈鑫,沈锡城.基于SOA的协同政务信息管理系统架构分析[J].中国水运月刊,2012,12(3):70~71.

[3]张铁峰,吕越颖,吕欣,等.基于面向服务架构的线损管理系统设计[J].电测与仪表,2014(22):1~6.

篇4

很多领域中都会进行项目管理,而且经过多年的研究和总结已经具有了相对比较成熟的体系。项目管理的方式和网络技术的有机结合已经成为提升企业管理水平,促进企业经济发展的重要因素。网络上的项目管理工作不仅降低了管理工作的复杂程度,还可以在第一时间实现信息和数据资源的高度共享。

1 网络计划技术概述

所谓的网络计划就是科学性相对较强的管理方式。一般来说,管理方式比较多,比较常见的就是关键路径和计划评审。这两种管理方式之前存在着一定的联系性,但是也有区别。二者都属于肯定型的作业方式,计划评审技术具有三个数值,关键路径技术则只需要一个数值即可。在具体应用的过程中,如果项目具有一定的危险性,则主要选择的是计划评审技术。如果项目对于时间的精准度提出了较高的要求,研究人员则优先选择关键路径方法。可见,二者的应用方式不同,针对性较强。

2 通信工程建设管理的现状分析

2.1 工程建设前期准备不够充分

对于现如今的通信工程来说,在前期建设阶段,由于工期相对较紧,而且人们往往以具体的工程为主,因此,前期的准备工作往往被严重地忽视。在不断施工的过程中,这一阶段的问题和弊病就逐渐暴露出来。

2.2 工程建设管理方法不科学

由于通信工程在实际的施工中会分布在不同的地区内,而且还会涉及到各种不同类型的领域。因此,工期会受到严重地制约,管理方法在实际的应用中有所差别。无论是在对资源进行整合的过程中还是对工程进行管理的过程中都需要采用科学的方法。但是,从目前工程建设的现状中可以看出,工程管理只是依靠工作人员的管理经验,还没有真正投入科学的管理方法。而且在通信工程施工之后也没有进行具体地评估和审定,大大地降低了我国通信工程的整体质量。

2.3 工程建设的复杂性较强

对于通信工程来说,其本身的复杂性较强。主要是由于工程涉及到内容较多,除了基站单项工程之外,还有电源单项工程。在工程建设的过程中,工作人员需要对通信行业的市场情况进行分析。

2.4 工程建设组织结构精炼程度不够

对于通信工程来说,部门和各个建设环节相互连接是一项重要的内容。这一过程需要很多管理人员,主要的工作任务就是对企业管理中各种数据信息以及监控信息等方面进行管理和控制。在这一过程中,很多部门的工作人员都会受到利益的影响,无视运作成本。可见,通信工程的组织结构还没有达到一定的精炼程度。

2.5 工程建设人员技术水平低

在通信工程建设的过程中,由于工作人员数量较多,工作环节比较复杂,因此分工比较精细。这在某种程度上延长了具体的运作时间,而且极大地增加了成本量。不仅如此,工作人员的工作内容也表现出一定的枯燥性,久而久之,工作积极性降低。另外,工作人员本身所拥有的技能水平也相对较低,在实际的通信工程建设工作中无法发挥作用。

3 网络计划技术在移动通信工程建设中的应用

3.1 各项工作的定义

在通信工程建设中包括较多的工作环节,以下是网络计划技术对各环节工作的定义。

第一,市场需求分析。市场需求分析主要是市场部针对市场的未来发展规划所提出网络容量的需求以及所覆盖的需求,同时还有运行维护部针对各种需求的维护所提出的网络指标。除此之外,还有客服部门针对用户的不同投诉所提出的网络覆盖盲点。

第二,可行性研究。可行性研究主要是针对实际的市场需求进行分析,并使用合理的网络规划与优化的软件对网络进行设计。其中分析的主要内容就是话务的分布均匀与否,利用网络优化解决还是增加基站解决。与此同时,还应对其实际的经济效益进行全面的分析。

第三,初步设计。初步设计主要是基于对市场需求的分析以及可行性的研究上,需要由专业的设计单位进行设计,并进行科学正确的施工指导。

第四,系统初验。在完成系统的割接以后,需要由工程建设的相关部门进行组织,并采取公司验收小组的方式对系统工程的实体与档案的归档工作进行验收。

第五,系统试运行。完成系统初验以后,运行维护部门可以在已经割接入网的设备进行一定的维护,并且及时的记录在实际运行过程中的问题,针对问题进行及时的解决与处理。

第六,系统终验。在系统完成试运行以后,与工程建设移动通信相关部门进行试运行过程中发现的问题。

第七,财务结算。财务结算就是企业内部的财务部门针对相关的工程结算要求,工程的建设部门与运行维护的部门将设备移交,并由工程的建设部门完成到货的证明以及相关文件。财务部将整体工程建设的总额进行结算,并上报给上级的主管部门。

第八,竣工验收。对所完成建设的工程进行实体的验收,并对竣工的文档以及财务的结算进行综合性的验收。

3.2 合理编写制定通信工程建设的工作表

在完成对通信工程建设各环节的工作定义后,能够根据相应的逻辑关系编制各环节工作的关系表,并确定各环节工作的正确顺序。完成工作定义以后,需要编制工作的清单,其中内容需要包括项目全部的工作内容,并进行各项工作的详细文字说明,这样才能保证项目内容的完整与准确,并能够合理的对各项工作进行了解。

3.3 依据工程建设整体路线计算工程完成日期

根据以上整体网络图以及子网络图进行分析,可以判定工程建设需要进行330天。在经过科学合理的可行性分析后,可以启动初步设计与基站单项工程以及传输线路工程三部分。因此,对通信工程建设工期的优化,最重要的就是突破网络图的关系,进而使各环节的工作进行有效的衔接。

结束语

总而言之,我国的通信技术和通信水平在不断提升,将网络计划技术应用到通信工程当中是一种必然的趋势。不仅可以提升通信工程数据管理的高效性,同时还可以将更为先进的管理技术应用到通信工程当中。在降低通信工程运行成本的基础上,保证运行的安全性和可靠性,同时还可以达到既定的目标,促进通信工程的发展。本文所提到的网络计划技术在通信工程当中的应用情况具有一定的现实性,希望能够给相关的研究人员提供帮助。■

参考文献

[1]杨程.移动通信工程项目进度管理研究[D].贵阳:贵州大学,2010.

篇5

1 引言

信息化技术的发展促进了各个领域的进步,如通信工程产业成为了经济发展的基础支撑,影响着人们的生活。构建通信工程项目管理系统,是通信工程良好运行的保障,能实现通信工程项目管理的自动化、智能化和高效化。因而分析通信工程项目管理系统的需求、设计和实现,对于提高其管理应用的水平有着积极的意义。

2 通信工程项目管理的需求分析

通信工程项目管理的需求主要有功能需求、性能需求、运行需求等,定义着通信工程项目管理系统的设计目标,以下做简要的分析。

2.1 功能需求分析

功能需求规划着通信工程项目系统的基本服务能力,为进度安排、投资、资源配制、跟踪、风险分析等打下基础,功能需求的要求比较多,作为项目查询和统计的必要支持,发挥着基础的作用。功能需求主要有系统登录、合同资金管理、项目立项管理、施工管理、工程管理、审计管理、物资采购管理、用户管理、系统设置管理等方面的内容。精确定位通信工程项目管理系统的功能需求,对于其构建有着重要的意义,便于建设高效、准确的管理系统,其工作的流程如下图1所示。

图1 系统管理功能分析

2.2 性能需求分析

性能需求分析要保证数据的精确度、兼容性两个方面的内容。兼容性:系统需要与操作性能相互兼容,如实现与windows、Linux、Unix等操作系统的兼容,满足用户对系统的实用和升级的要求,具备良好的适应性。数据精确度:通信工程项目管理系统是一个工作管理的平台,要各项数据保证精确性,才能确保工作的流畅正确,如合同进度安排精确、合同资金精确、施工统计查询精确等,数据的精确性是保证性能的基础。

2.3 运行需求分析

运行需求分析主要是软硬件接口和用户体验两个方面,如软硬件接口:硬件服务器实现对Windows、Linux、Unix等平台下软件的兼容,软硬件的接口工作状态稳定。如用户体验方面:系统自带浏览器,用户不需要安装插件,登录即可实现对管理系统的操作和访问,并且操作功能齐全,可以在界面化的操作下完成。

2.4 其他需求分析

其他需求主要有安全可靠性需求和易用性需求,如安全可靠性需求:通信工程项目的管理系统要求具有较高的保密性和安全性,对于项目合同、项目数据等保护力度大,因而在设计系统时,从用户权限、登录等方面要考虑相应数据的安全性,为可靠性做出足够的设计。系统的易用性需求:项目管理系统的使用者一般为普通的工作人员,信息化方面的技能并不高,因而要确保系统的易用性,如登录简易、界面优化等,需要保证一般的工作人员能很好的应用该系统。

3 通信工程项目管理系统的设计

3.1 系统结构的设计

系统结构是系统的重要定义,可以看作是系统目标下层的功能集合,对每个子系统还可以再分层,实现功能的细化,越下层的功能就越具体。系统结构的设计顶层为宏观定义,逐渐的分解细化,将每一个功能模块分配到子系统中,按从属关系进行定义划分。通信工程项目管理系统被分解为施工管理、合同资金管理、用户管理、项目立项管理、审计管理、物资采购管理、系统设置管理等。

3.2 系统功能模块的设计

(1)系统登录设计:限制未授权或注册用户的权限,外网用户登录需要进行身份验证,登录的各项信息在后台比对完整、正确后才能提交,否则将出现错误提示,确保系统登录的安全性。

(2)项目立项管理:一个项目申报、审核的完整流程,按照流程化的设计思路和方式进行。

(3)合同资金管理:管理工程合同的资金,对财务进行编码,方便查询和操作工程资金管理。

(4)施工管理:具备工程变更、开工报告、停工申请、复工申请、工期调整、竣工验收申请等模块。

(5)物资采购管理:为了确保采购的高效,主要有采购任务管理、工程物料变更通知管理、工程用料招投标管理等模块。

(6)工程管理:有工程管理登录、物料状态查询、施工任务、审核等模块。

(7)审计管理:在管理系统中设置具体的流程,如施工方提交工程建设部门,工程部门初审、复审,主管审核提交部门经理,部门经理提交总经理,总经理提交财务部门等一系列的程序。

3.3 数据库的设计

数据库的设计要建立在系统需求分析的基础上,根据功能设计,做出系统数据库结构的设计,如部门信息表、部门主管信息表、员工信息表、项目分类信息、项目信息表、物料采购信息表、服务合同信息表、建设单位人员信息表、管理员信息表等。

4 通信工程项目管理系统的实现

通信工程项目管理系统的实现主要有系统的开发环境、工程管理系统两大内容。

4.1 系统的开发环境

要从软硬件两个方面进行分析,也是系统开发的基本要素,如系统的硬件环境:采用个人电脑虚拟服务器端进行运行,硬盘空间、内存大小、CPU等都做了较为明确的规定,需要达到一定的硬件配置才能运行。如在系统的开发的软件环境:采用个人电脑,操作系统一般为Windows7,数据库和服务器都做了规定,某些特殊的需求下,也有运用Linux或Unix等系统。

4.2 通信工程项目管理系统的实现

通过对通信工程项目管理的系统进行需求分析和模块设计之后,然后研究系统的实现。

(1)系统登录页面的实现:页面采用了Dreamweaver 10.0进行,页面的设计简洁明晰,CSS样式统一了风格,并对页面进行渲染。

(2)项目立项管理:登录后,工作人员可以进行项目受理、浏览、立项申请书的查看审核等,界面中有审核、通过等操作。

(3)合同资金管理实现:通过接收、审核、财务编码、合同凭证等功能,随时查询和了解相关的资料。

(4)施工管理:展开菜单,如工程变更、停工、复工等,都可以在子菜单中点击操作,并且可以隐藏。

(5)物资采购管理实现:进入物资采购管理子菜单,可以提交采购计划、审核等操作。

(6)工程管理实现:用户登录后,有权限进行施工管理的操作,如工程材料查询、起草等。工程管理需要注重界面的优化,便于工程人员操作。

(7)审计实现:对凭证、文书等查看,进行监督。审计人员进入系统需要一定的权限,可以对登录的用户进行分类管理,审计涉及到财务、工程资料等多方面的内容,因而要做好保密性的工作。

5 结束语

通信工程项目管理系统对于通信工程而言具有重要的作用,信息化的工作方式能提高效率,减少资源的浪费,并且能很好的适应复杂变化的市场环境。着手通行工程项目管理的系统设计,并研究实现的方式,对于提高通信工程管理的水平和效益具有积极的作用。

参考文献:

友情链接